11 min read
From a three-person office in Accra in 2002 to a 6,000-employee, seven-subsidiary conglomerate spanning construction, insurance, hospitality, banking, commodities, bitumen, and energy, the wholly Ghanaian-owned First Sky Group has become a symbol of indigenous industrial capability. Its crowning achievement: the 50MW Galgu solar plant in Yendi, built entirely by Ghanaian engineers, which went live in 2026 and stands as the first fully Ghanaian-owned utility-scale solar project in the country.
Executive Introduction
On a January afternoon in 2026, President John Dramani Mahama stood before an interdenominational thanksgiving service in Accra to mark the 23rd anniversary of a company he had watched grow from its earliest days. His message was unambiguous: First Sky Group is what Ghanaian enterprise can achieve when given the opportunity .
Key Takeaways
- Its crowning achievement: the 50MW Galgu solar plant in Yendi, built entirely by Ghanaian engineers, which went live in 2026 and stands as the first fully Ghanaian-owned utility-scale solar project in the country.
- Executed by First Sky Limited under an Engineering, Procurement, Construction with Financing (EPCF) arrangement with the Bui Power Authority, the $59 million facility was completed in September 2026 and connected to the national grid.
- The Galgu solar plant is a 50MWp solar photovoltaic facility in Yendi, Northern Region, executed by First Sky Limited for the Bui Power Authority under an EPCF arrangement.
The numbers bear him out. What began in 2002 as a three-person operation in a 4×4 office has become a wholly Ghanaian-owned conglomerate with over 6,000 employees nationwide, operating across construction, insurance, hospitality, commodities, energy, bitumen processing, and rural banking . Its subsidiaries include First Sky Construction (a first-class road contractor), Serene Insurance (the fastest-growing insurer in Ghana), Volta Serene Hotel (the only four-star hotel in the Volta Region), Frerol Rural Bank, First Sky Commodities (processing 25,000 metric tonnes of cocoa annually), and First Sky Energies.
But the achievement that has most captured national attention is the 50MW Galgu solar photovoltaic plant in Yendi, Northern Region. Executed by First Sky Limited under an Engineering, Procurement, Construction with Financing (EPCF) arrangement with the Bui Power Authority, the $59 million facility was completed in September 2026 and connected to the national grid. Crucially, the entire construction was undertaken by Ghanaian engineers, without foreign technical support .
“I did not know that an indigenous Ghanaian company had the capacity to execute such a project,” said Emmanuel Kwasi Bedzrah, Chairman of Parliament’s Energy Committee, after inspecting the facility .
This profile examines First Sky Group’s 23-year evolution, its seven-subsidiary structure, the Galgu solar plant’s significance for Ghana’s energy transition, its leadership under Apostle Eric Seddy Kutortse, its corporate philanthropy (including GH¢51 million for dialysis patients), and the question that now defines its trajectory: Can an indigenous conglomerate built on construction and faith-based values lead Ghana’s green energy future?
Company Overview: From Three Employees to Six Thousand
The Genesis: 2002 and the 4×4 Office
First Sky Group’s origin story is one of modest beginnings and deliberate growth. The company started in 2002 with a workforce of just three personnel operating from a 4×4 office in Accra . Its founder, Eric Seddy Kutortse, built the business on a simple premise: serve Ghana, humanity, and God, with a focus on job creation and national development .
The Group’s corporate structure evolved through deliberate diversification. Its subsidiaries were established over time:
| Subsidiary | Sector | Established/Status |
|---|---|---|
| First Sky Construction Limited | Road construction, civil engineering | Core subsidiary |
| First Sky Commodities Limited | Cocoa trading (Licensed Buying Company) | 2015 |
| Volta Serene Hotel | Hospitality (4-star luxury) | 2015 |
| Serene Insurance Company | General insurance | 2018 |
| First Sky Bitumen Processing Limited | Bitumen processing | 2018 |
| Frerol Rural Bank | Rural banking (Kpando, Volta Region) | Operational |
| First Sky Energies Limited | Renewable energy | Operational |
The Ownership and Leadership
First Sky Group is a wholly Ghanaian-owned holding entity . Its Executive Chairman and Founder is Apostle Eric Seddy Kutortse, who has led the company since its founding and is also a religious leader . The Group’s corporate identity is explicitly faith-based—its 23rd-anniversary theme was “Proclaiming the Mighty Deeds of the Lord,” and Kutortse has described the company as founded to serve “Ghana, humanity and God”.
Key Operational Metrics (2026)
| Metric | Value |
|---|---|
| Founded | 2002 |
| Founder & Executive Chairman | Eric Seddy Kutortse |
| Ownership | Wholly Ghanaian-owned |
| Employees | 6,000+ (nationwide) |
| Subsidiaries | 7 |
| Sectors | Construction, Insurance, Hospitality, Banking, Commodities, Bitumen, Energy |
| Key Energy Project | 50MW Galgu Solar Plant, Yendi ($59 million) |
| CSR Commitment | GH¢51 million+ for dialysis patients (8 years) |
The Galgu Solar Plant: Indigenous Engineering on a National Scale
The Project
The 50MW Galgu solar plant in Yendi Municipality, Northern Region, is First Sky Group’s most significant achievement to date. The $59 million facility was executed under an EPCF (Engineering, Procurement, Construction with Financing) arrangement with the Bui Power Authority (BPA) .
Key details:
| Feature | Detail |
|---|---|
| Capacity | 50 MWp |
| Location | Galgu, Yendi Municipality, Northern Region |
| Cost | $59 million |
| Contract Model | EPCF with Bui Power Authority |
| Construction Completed | September 2026 |
| Grid Connection | Connected to national grid |
| Execution | Entirely by Ghanaian engineers, no foreign technical support |
Why It Matters
The Galgu plant is not merely another solar installation. It is a proof of concept for indigenous technical capacity. As Kutortse stated: “With the completion of the 50MW Solar PV generating power station constructed with wholly Ghanaian engineers, the case had been made strongly for local expertise to fully take charge of the energy environment of the country” .
The Parliamentary Select Committee on Energy and Mines, which inspected the facility, acknowledged that the project demonstrated what indigenous Ghanaian companies could achieve when given the opportunity .
The BPA’s Director of Engineering, Peter Acheampong, noted that the plant would contribute to reducing carbon emissions and disclosed that the BPA board had approved an additional 300MWp of solar capacity in northern Ghana .
The Yendi 140-Acre Site
The Galgu plant spans 140 acres of land in Yendi, representing what Kutortse described as “confidence in Ghanaian entrepreneurship” and alignment with the Sustainable Development Goal on affordable and clean energy .
The Subsidiary Portfolio: A Diversified Indigenous Conglomerate
First Sky Construction: The Road Builder
First Sky Construction Limited is a first-class road construction and civil engineering firm . It has been the beneficiary of government policies prioritising indigenous contractors. President Mahama recalled that during his first term, his government deliberately awarded road projects to qualified local firms, and First Sky was among those that grew to international standards .
The company was awarded the Atimpoku–Asikuma–Anyirawase–Ho–Denu–Aflao 117.4-kilometre road project, which the President cited as evidence of First Sky’s quality and speed . The second tranche of the Accra motorway towards Central University was also awarded to First Sky under the Big Push programme .
Serene Insurance: The Fastest-Growing Insurer
Serene Insurance Company Limited is a general insurance firm and a subsidiary of First Sky Group . It has been adjudged the fastest-growing insurance company in Ghana class=””> and has met the new minimum capital requirements . In 2026, Serene pledged GH¢2 million in cash alongside a GH¢20 million insurance package for Ghana’s Black Stars ahead of the World Cup .
Volta Serene Hotel: Hospitality in the Volta Region
Volta Serene Hotel is a four-star luxury hotel in Ho, the only four-star hotel in the Volta Region . It won the “4 Star Hotel of the Year” award at the 2024 Volta Regional Tourism Awards, while First Sky Group won Corporate Organisation of the Year . The Group has plans for an Oti Serene Resort .
Frerol Rural Bank: Community Banking
Frerol Rural Bank is a thriving rural banking institution based in Kpando, Volta Region, with an additional branch in Ho . It serves as a vehicle for community philanthropy, including a GH¢60,000 donation of phototherapy machines and relief items to health and special needs institutions in Kpando .
First Sky Commodities and Bitumen Processing
First Sky Commodities Limited is a Licensed Buying Company in Ghana’s cocoa sector, processing 25,000 metric tonnes of cocoa annually . First Sky Bitumen Processing Limited operates in bitumen processing, supporting road construction .
Leadership: Apostle Eric Seddy Kutortse
Eric Seddy Kutortse is the Founder and Executive Chairman of First Sky Group . His leadership blends business acumen with religious conviction. The company’s anniversary celebrations are structured as thanksgiving services, and Kutortse has been honoured by the Trinity Temple Assemblies of God Church with the Trinity Excellence Award in Missions for his dedication to the church .
His business philosophy is rooted in national service. At the 23rd anniversary, he stated that the Group was founded to serve “Ghana, humanity and God, with a focus on job creation and national development”.
His commitment to indigenous capacity is evident in the Galgu solar project. “The nation boasted enough local capacity to deliver present and future energy projects to accelerate economic development,” he said after the plant’s completion .
Corporate Philanthropy: GH¢51 Million for Kidney Care
First Sky Group’s corporate social responsibility is concentrated in healthcare, particularly kidney treatment. Kutortse disclosed that the Group had committed over GH¢51 million in the past eight years to support dialysis patients at Korle Bu Teaching Hospital and sponsored six kidney transplants in the previous year .
In October 2026, the Group’s subsidiary Serene Insurance handed over a renovated 5th Floor of Korle Bu’s Surgical Department, and Kutortse announced that renal patients would benefit from free kidney transplants funded by the Group .
The Group also built 101 churches, reflecting its faith-based mission .
Challenges and Risks
Risk 1: Concentration in Construction and Government Contracts
A significant portion of First Sky’s revenue derives from government road contracts. Changes in government spending priorities or political transitions could affect the construction pipeline.
Risk 2: Energy Project Execution and Financing
The Galgu solar plant was executed under an EPCF arrangement, meaning First Sky provided financing. The company’s ability to recover its investment depends on the Bui Power Authority’s payment terms and the plant’s operational performance.
Risk 3: Regulatory and Licensing Risks
Serene Insurance operates in a regulated sector and must maintain capital adequacy. Frerol Rural Bank is subject to Bank of Ghana oversight.
Risk 4: Currency and Macroeconomic Volatility
Construction and energy projects require imported equipment and materials, exposing the Group to cedi depreciation.
Risk 5: Governance and Succession
As a founder-led conglomerate with a strong religious identity, First Sky faces questions about succession planning and the separation of church and business governance.
Future Outlook
First Sky Group’s trajectory points toward deeper involvement in Ghana’s energy transition. The BPA has approved an additional 300MWp of solar capacity in northern Ghana, and First Sky’s proven capability positions it as a likely contractor for future phases .
The Group’s construction pipeline includes major road projects under the Big Push programme . Serene Insurance continues to expand, and the hospitality portfolio may grow with the Oti Serene Resort .
The core question is whether First Sky can transition from a construction-led conglomerate to a diversified industrial group with energy as a pillar—without overextending its balance sheet or losing the quality that earned it the President’s endorsement.
Last Updated on November 11, 2026 by Samuel Kwame Boadu
Disclaimer: Some content on Accra Street Journal may be aggregated, summarized, or edited from third-party sources for informational purposes. Images and media are used under fair use or royalty-free licenses. Accra Street Journal is a subsidiary of SamBoad Publishing Hub under SamBoad Business Group Ltd, registered in Ghana since 2014.
For concerns or inquiries, please visit our Privacy Policy or Contact Page.
Samuel Kwame Boadu is a Ghanaian media entrepreneur and storyteller with a passion for amplifying urban voices and uncovering everyday truths. He is the Editor-in-Chief and Founder of Accra Street Journal, a dynamic digital platform dedicated to capturing the pulse of Ghana’s capital—its people, culture, challenges, business, sports and innovations.
Use the following reference when citing or referencing this article.
Your feedback helps us improve our journalism.
Report an Error
Help us maintain accuracy. Let our editorial team know if you spot an issue in this article.