Dangote and Afreximbank Join Sierra Leone's $6.1 Billion Port and Rail Plan

Dangote and Afreximbank Join Sierra Leone’s $6.1 Billion Banana Island Port and Rail Plan

Sponsored

Apex Insurance Brokers

 


4 min read

Dangote Group and Afreximbank have signed a memorandum of understanding with Sierra Leonean developer Gento Group to advance a deep-water port at Banana Island, a logistics hub at Kent and a railway linking the coast to mining regions — though the agreement discloses no financing commitment.

Dangote Group and Afreximbank have joined Sierra Leonean developer Gento Group in an agreement to advance plans for a deep-water port at Banana Island, a logistics hub at Kent and a railway linking the port to mining regions.

✦

Key Takeaways

  • The summit's close-out statement, circulated by Sierra Leone's State House Media and Communications Unit, put the sponsor's estimate for the port-and-rail programme at about $6.1 billion.
  • Guinea is separately pursuing a $1.9 billion deep-water port designed to serve miners, container traffic and industry, alongside the Simandou iron-ore development.
  • The MoU discloses no financing commitment, party investment amounts, specific roles or construction start date, arriving as Guinea pursues a separate $1.9 billion deep-water port alongside the Simandou iron-ore development.

The parties signed a memorandum of understanding (MoU) on November 17 at the West Africa Integration and Investment Summit in Lungi.

The agreement advances the project’s development, but it does not disclose how much any party will invest, their specific roles or when construction will begin.

The Cost Estimates

The summit’s close-out statement, circulated by Sierra Leone’s State House Media and Communications Unit, put the sponsor’s estimate for the port-and-rail programme at about $6.1 billion.

ADWUMAFIE JOB JOB OPPORTUNITY
Insurance Sales Agent (Commission-Based) – Danniads Limi
Danniads Limi · Ghana · Freelance
Powered by Adwumafie View Job →

A Gento project update in October described a $2.7 billion port** and a **$3.2 billion railway, or $5.9 billion combined.

That the estimate has moved from $5.9 billion to $6.1 billion within a month — before any engineering design has been finalised — is worth noting. Large infrastructure estimates commonly escalate between feasibility and financial close; the direction here is consistent with that pattern.

The Existing Concession

The port is not a new proposal.

Sierra Leone’s Parliament ratified a concession agreement with Gento in July 2024 covering the design, financing, construction and operation of a Banana Island seaport and a terminal at Kent.

At the time, the transport minister estimated the port alone at about $2 billion and said the government would receive a 10% share.

Sponsored

feezeka

The gap between the 2024 port estimate of $2 billion and the current $2.7 billion figure suggests either scope expansion or cost inflation — neither of which has been publicly explained.

The Project Specifications

Gento says the planned port would have a depth of about 22 metres and accommodate larger vessels.

Sponsored

Its rail proposal would connect the coast to mineral-producing areas, including Tonkolili.

A Dutch port consultancy, Maritime & Transport Business Solutions, completed a feasibility assessment for Gento between May and October 2024, including market, traffic and financial analysis.

The Regional Context

The project arrives as West African countries seek infrastructure to move minerals and other goods to international markets.

Guinea is separately pursuing a $1.9 billion deep-water port designed to serve miners, container traffic and industry, alongside the Simandou iron-ore development.

Reuters reported that Guinea was seeking interest from US, Chinese and multilateral financiers, while Sierra Leone’s new MoU does not disclose a financing commitment.

What the MoU Does and Doesn’t Do

For Dangote and Afreximbank, the agreement brings two of Africa’s most active infrastructure and industrial financiers into a project that has struggled to move from concession to construction since 2024.

For Sierra Leone, the involvement of a billionaire industrialist and a multilateral trade finance institution provides credibility that a domestic developer alone could not supply — but credibility is not capital.

The absence of disclosed financing, defined party roles or a construction timeline means the project remains at the development-discussion stage, nearly two and a half years after parliamentary ratification.

Quick Facts

Gento Group, Dangote Group and Afreximbank signed an MoU on November 17 at the West Africa Integration and Investment Summit in Lungi to advance a Banana Island deep-water port, a Kent logistics hub and a railway to mining regions, with the sponsor’s estimate at about $6.1 billion per Sierra Leone’s State House close-out statement.

A Gento October update put the port at $2.7 billion** and the **railway at $3.2 billion ($5.9 billion combined)**, while Sierra Leone’s **Parliament ratified Gento’s concession in July 2024**, when the transport minister estimated the port at about **$2 billion with a 10% government share.

Sponsored

SAMBOAD

The planned port would have a 22-metre depth to accommodate larger vessels, with rail connecting to Tonkolili and other mineral areas, following a feasibility assessment by Maritime & Transport Business Solutions between May and October 2024.

The MoU discloses no financing commitment, party investment amounts, specific roles or construction start date, arriving as Guinea pursues a separate $1.9 billion deep-water port alongside the Simandou iron-ore development.

Source: Accra Street Journal

Last Updated on November 23, 2026 by Samuel Kwame Boadu

🏢
ASJ COMPANY INTELLIGENCE Know the Companies Behind the Headlines Search Ghana's business database.
EXPLORE →
📍
ACCRA STREET DIRECTORY Find It. List It. Discover Accra. Find local businesses or get your business discovered.
EXPLORE →
✅ Others are getting FREE JOBS + TIPS on our WhatsApp channel. Join now!

Disclaimer: Some content on Accra Street Journal may be aggregated, summarized, or edited from third-party sources for informational purposes. Images and media are used under fair use or royalty-free licenses. Accra Street Journal is a subsidiary of SamBoad Publishing Hub under SamBoad Business Group Ltd, registered in Ghana since 2014.

For concerns or inquiries, please visit our Privacy Policy or Contact Page.

Cite This Article

Use the following reference when citing or referencing this article.

Author Samuel Kwame Boadu
Published November 23, 2026
Publisher Accra Street Journal
JOBS + DIRECT ARTICLES Get job opportunities and read ASJ articles directly on WhatsApp.
Join WhatsApp Channel
Was this article helpful?

Your feedback helps us improve our journalism.

Report an Error

Help us maintain accuracy. Let our editorial team know if you spot an issue in this article.

Report a problem with this article

Your report is sent privately to the Accra Street Journal editorial team.

Sponsored

error: Content is protected. Kindly credit Accra Street Journal when referencing.
ASJ FOOTBALL
Loading scores…
Loading live matches…
Loading today's fixtures…
Loading today's results…