An Accra Street Journal Real Estate Intelligence Brief
Executive Introduction
The 4-bedroom house represents a significant step up from starter homes—it is the configuration most associated with middle-class and upper-middle-class family living in Ghana. Whether you are building a detached house for your family in Accra, a rental property in Kumasi, or a home in a developing suburb, understanding the real cost is essential to avoiding the “completeness gap” that has stalled countless projects mid-construction.
This ASJ report provides a comprehensive, data-driven breakdown of the real cost of building a 4-bedroom house in Ghana in 2026. Drawing on the Ghana Statistical Service’s Prime Building Cost Index (PBCI), the GhanaHousePlanner parametric cost model validated by the University of Cape Coast and KNUST, and current market prices for key materials, we provide a realistic framework for budgeting, phasing construction, and avoiding costly underestimates.
📢 GET A DETAILED ARTICLES + JOBS
Join ASJ's WhatsApp Channel and never miss a post or opportunity.
Part 1: The Current Economic Context – Stable Costs, Selective Inflation
Building Inflation Trends (2025–2026)
The construction sector has experienced significant cost stabilisation after the volatility of 2023–2024. According to the Ghana Statistical Service’s Prime Building Cost Index (PBCI), building inflation has declined for nine consecutive months through January 2026 .
| Period | Year-on-Year Building Inflation | Key Drivers |
|---|---|---|
| January 2025 | 23.7% | Peak of post-COVID construction cost surge |
| March 2025 | 24.4% | Highest recorded rate |
| December 2025 | 4.4% | Sharp moderation |
| January 2026 | 3.9% | Ninth consecutive monthly decline |
| April 2026 | 2.2% | Continued stability |
The April 2026 PBCI stood at 136.1, up from 133.2 in April 2025, representing a modest 2.2 per cent annual increase in construction costs. Month-on-month, prices increased by 1.5 per cent between March and April 2026 .
Key takeaway: Construction costs have stabilised significantly compared to the 2024 peak, but monthly increases continue. This suggests that while the sector is no longer in crisis, costs are still trending upward gradually.
Material-Specific Inflation: Winners and Losers
Not all construction materials are moving in the same direction. The PBCI data reveals significant divergence :
Declining Costs (Deflation):
| Material | Year-on-Year Inflation (April 2026) | Implication |
|---|---|---|
| Cement | -11.2% | Prices have dropped significantly |
| Steel | -3.6% | Structural steel costs easing |
| Fine aggregate | -8.7% | Sand and gravel costs down |
Rising Costs (Inflation):
| Material | Year-on-Year Inflation (April 2026) | Implication |
|---|---|---|
| Glazing | +16.2% | Windows and glass work are major cost drivers |
| Plumbing | +14.5% | Pipes, fittings, and sanitary ware |
| Roofing sheets | +13.0% | Roofing materials continue to climb |
| Electrical works | 52.8% of total sector inflation | Single largest inflation contributor |
| Surface finishes/tiles | 10.8% (January) | Floor and wall tiling costs rising |
The Government Statistician’s advice is clear: “Households planning construction should take advantage of lower prices for materials such as cement and steel, while carefully budgeting for high-cost items including glazing, plumbing and roofing sheets” .
Part 2: Cement and Steel – The Foundation of Your Budget
Current Cement Prices (June 2026)
Cement is the lifeblood of any construction project. As of June 2026, cement prices in Ghana have stabilised after significant declines from the 2024 peak .
| Cement Type | Current Price (per 50kg bag) | Primary Use |
|---|---|---|
| 32.5R Cement | GHS 80 – GHS 85 | Block moulding, plastering, flooring |
| 42.5R Cement | ~GHS 107 | Beams, columns, slabs (structural elements) |
Price comparison: In the first half of 2024, cement surged from GHS 85 to GHS 110, driven largely by cedi depreciation and high inflation . By January 2026, prices had dropped, with 32.5R falling from GHS 90–95 to the current GHS 80–85 range . A builder who bought 40 bags in 2024 paid over GHS 4,200; the same 40 bags in early 2026 cost about GHS 3,400—a saving of nearly GHS 1,200 .
How many bags for a 4-bedroom house? A 4-bedroom house of standard size (approximately 150–200 m²) requires between 1,200 and 2,000 bags of cement, depending on design complexity (bungalow vs storey building), number of storeys, and finishing standards.
| Construction Phase | Estimated Cement Bags |
|---|---|
| Foundation | 250–400 |
| Blockwork (walls) | 500–800 |
| Columns, beams, lintels | 200–350 |
| Flooring and screeding | 150–250 |
| Plastering (rendering) | 100–200 |
| Total Estimate | 1,200–2,000 bags |
Estimated cement cost: GHS 96,000 – GHS 214,000
Steel Reinforcement (Iron Rods) Prices
High tensile steel reinforcement (iron rods) is another major cost driver. In the 2026 market, prices range between GHS 19,000 and GHS 25,500 per ton .
How much steel does a 4-bedroom house need? A typical 4-bedroom house requires:
| Structural Component | Steel Tonnage Estimate |
|---|---|
| Foundations (strip or raft) | 3.5–5.5 tons |
| Columns and lintels | 2–3.5 tons |
| Ring beams | 2–3 tons |
| Total Estimate | 7.5–12 tons |
Estimated steel cost: GHS 142,500 – GHS 306,000
Part 3: The “Completeness Gap” – Why Contractor Quotes Are Misleading
A 2026 study from the University of Cape Coast and Kwame Nkrumah University of Science and Technology identified what researchers term the “completeness gap” —a systematic discrepancy between informal contractor quotes and actual construction costs .
The “completeness gap” arises from the omission of essential components in informal quotes :
| Omitted Component | Why It’s Essential |
|---|---|
| Structural steel (Y16 rebar) | Required for foundations, columns, beams, and slabs. Without it, the building cannot meet code requirements for structural integrity. |
| Plastering (rendering) | Protects blockwork from weather and provides a surface for painting or finishing. |
| Floor screeding | Provides a level, smooth surface for flooring installation. |
| Full electrical services | Wiring, conduits, distribution boards, switches, and fixtures. |
| Full plumbing services | Piping, fittings, water storage, sanitary ware, and drainage. |
The critical warning: Per-square-metre rates rarely cover the requirements for a fully completed, code-compliant building . If a contractor quotes you a flat rate per square metre, assume they are omitting critical components—and budget accordingly.
Part 4: Comprehensive Cost Breakdown for a 4-Bedroom House
Based on the GhanaHousePlanner model, which uses seven calculation modules (foundation, blockwork, cement, structural steel, roofing, plumbing, and electrical) , we provide the following estimated cost ranges for a standard 4-bedroom house of approximately 150–200 square metres in Greater Accra in 2026.
Total estimated construction cost range (turnkey finish): GHS 650,000 – GHS 1,400,000
Note: This range excludes land acquisition costs, which vary dramatically by location (see Part 6).
Phase 1: Site Preparation and Foundation
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Site clearing and levelling | 10,000 – 30,000 | Varies by site condition |
| Excavation (foundation trenches) | 8,000 – 18,000 | Excavator hire ~GHS 6,000 |
| Hardcore filling and compaction | 10,000 – 25,000 | |
| Concrete works (foundation) | 35,000 – 70,000 | Includes concrete mixing and pouring |
| Reinforcement (steel) | 60,000 – 120,000 | Estimated 3.5–5.5 tons at GHS 19k–25k/ton |
| Formwork (wood) | 12,000 – 25,000 | For foundation and column casting |
| Subtotal | 135,000 – 288,000 |
Note: Omak Heights Construction Company estimated that foundation work alone for a 4-bedroom house requires approximately GHS 39,200 for materials excluding cement, iron rods, binding wires, nails, DPC, and bitumen—which are additional .
Phase 2: Blockwork and Wall Construction
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Sandcrete blocks (6-inch) | 35,000 – 60,000 | Estimated 3,500–6,000 blocks |
| Sandcrete blocks (4-inch) | 12,000 – 25,000 | For internal partitions |
| Cement for blockwork | 35,000 – 60,000 | Estimated 400–700 bags at GHS 80–85 |
| Sand and gravel (sharp sand) | 15,000 – 35,000 | One trip of sand ~GHS 4,500 |
| Labour (masonry) | 35,000 – 55,000 | |
| Subtotal | 132,000 – 235,000 |
Phase 3: Columns, Beams, and Lintels (Structural)
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Reinforcement (steel) | 70,000 – 150,000 | Estimated 3.5–6 tons for columns, beams, lintels |
| Concrete (ready-mix or site-mixed) | 20,000 – 45,000 | |
| Formwork (wood) | 10,000 – 22,000 | |
| Labour | 15,000 – 30,000 | |
| Subtotal | 115,000 – 247,000 |
Phase 4: Roofing
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Roof timber (rafters, purlins) | 40,000 – 80,000 | Hardwood; avoid cheap wood that warps |
| Roofing sheets | 55,000 – 110,000 | Inflation at +13% |
| Ridge caps, flashings, nails | 12,000 – 25,000 | |
| Ceiling (PVC or gypsum) | 30,000 – 60,000 | |
| Labour (carpentry) | 20,000 – 40,000 | |
| Subtotal | 157,000 – 315,000 |
Phase 5: Flooring and Plastering
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Floor screeding | 15,000 – 35,000 | Omitting screed is a common “completeness gap” error |
| Floor tiles (ceramic or porcelain) | 35,000 – 80,000 | Surface finishes/tiles inflation at 10.8% |
| Wall plastering (rendering) | 40,000 – 75,000 | Internal and external |
| Subtotal | 90,000 – 190,000 |
Phase 6: Electrical Installation
Critical note: Electrical works account for 52.8 per cent of total sector inflation. This is the single largest cost driver in construction and the most commonly underestimated category .
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Wiring and conduits | 20,000 – 40,000 | |
| Distribution board (DB) | 7,000 – 15,000 | |
| Switches, sockets, fittings | 18,000 – 35,000 | |
| Lighting fixtures | 12,000 – 25,000 | |
| Labour (certified electrician) | 12,000 – 25,000 | |
| Subtotal | 69,000 – 140,000 |
Phase 7: Plumbing and Sanitation
Plumbing inflation is running at +14.5 per cent year-on-year .
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Piping (PVC and PPR) | 15,000 – 30,000 | |
| Water storage tanks | 8,000 – 25,000 | |
| Sanitary ware (toilets, sinks, showers) | 20,000 – 50,000 | |
| Water heater (optional) | 8,000 – 18,000 | |
| Labour (plumber) | 10,000 – 20,000 | |
| Subtotal | 61,000 – 143,000 |
Phase 8: Doors, Windows, and Glazing
Glazing inflation is running at +16.2 per cent—the fastest-rising cost component .
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| External doors (metal or wood) | 15,000 – 35,000 | |
| Internal doors | 10,000 – 25,000 | |
| Window frames | 18,000 – 45,000 | |
| Glass (glazing) | 15,000 – 35,000 | Highest inflation category |
| Subtotal | 58,000 – 140,000 |
Phase 9: Painting and Finishing
| Item | Estimated Cost (GHS) | Notes |
|---|---|---|
| Paint (internal and external) | 20,000 – 50,000 | |
| Labour | 10,000 – 22,000 | |
| Subtotal | 30,000 – 72,000 |
Part 5: Construction Cost Summary Table – 4-Bedroom House
| Phase | Estimated Cost Range (GHS) |
|---|---|
| Site preparation and foundation | 135,000 – 288,000 |
| Blockwork and wall construction | 132,000 – 235,000 |
| Columns, beams, lintels | 115,000 – 247,000 |
| Roofing | 157,000 – 315,000 |
| Flooring and plastering | 90,000 – 190,000 |
| Electrical installation | 69,000 – 140,000 |
| Plumbing and sanitation | 61,000 – 143,000 |
| Doors, windows, and glazing | 58,000 – 140,000 |
| Painting and finishing | 30,000 – 72,000 |
| Construction Subtotal | 847,000 – 1,770,000 |
| Contingency (15–20%) | 127,000 – 354,000 |
| Total Construction | 974,000 – 2,124,000 |
Industry estimate cross-check: Real estate firm T-Square Properties and Construction estimated that building a modern 4-bedroom house in Accra costs between GHS 800,000 and GHS 1.2 million (approximately $70,000–$105,000), depending on materials, design complexity, and contractor fees . This is broadly consistent with our lower-to-mid range.
Notes:
-
These estimates are based on 2026 market prices in Greater Accra.
-
Prices vary by contractor quality, finishing standards, and exact location.
-
The lower end assumes basic finishes and lower-tier materials; the upper end assumes higher-quality finishes and brand-name materials.
-
The “completeness gap” warns that quotes significantly below these ranges likely omit essential components .
Part 6: Land Acquisition – The Largest Variable
The cost of land in Accra varies dramatically by location and is often the single largest expense in a homebuilding project .
| Location | Land Price Range | Notes |
|---|---|---|
| East Legon | $80,000 – $150,000+ | “The gold standard.” No legitimate plot under $80,000 |
| Airport Residential | $100,000 – $200,000+ | Premium location |
| Cantonments | $80,000 – $150,000+ | Established residential area |
| Prampram | $15,000 – $30,000 | “Notorious for deed issues and litigation” |
| Dodowa | $10,000 – $20,000 | Developing area |
| Kasoa | $8,000 – $15,000 | Peri-urban, high availability |
| Amasaman | $5,000 – $12,000 | Affordable, distance from city centre |
Critical warning: “If someone offers you a plot for thirty thousand in East Legon you should walk away. You are buying a lawsuit and not a home” . Before purchasing any land, perform a search at the Lands Commission to verify ownership and title.
Additional Pre-Construction Costs
Before construction begins, factor in these essential expenses :
| Item | Estimated Cost (GHS) |
|---|---|
| Architectural Drawings and Structural Designs | 10,000 – 30,000 (depends on architect and design complexity) |
| Building Permits | 5,000 – 15,000 (based on municipality and project size) |
| Survey and Land Documentation | Varies by location and ownership status |
Part 7: Finished 4-Bedroom House Prices – Buying vs. Building
For comparison, the cost of buying an already-built 4-bedroom house in Greater Accra in 2026 ranges as follows :
| Location | Price Range (GHS) | Price Range (USD) | Market Segment |
|---|---|---|---|
| Emerging suburbs (Oyibi, Adenta, Kasoa, Tema Comm 25) | 1,200,000 – 2,500,000 | $109,000 – $227,000 | Starter/mid-range 4-bedroom homes |
| Established suburbs (East Legon Hills, Spintex, parts of Tema) | 2,500,000 – 4,500,000 | $227,000 – $409,000 | Better finishes, estate amenities |
| Prime Accra (East Legon, Dzorwulu, Airport Residential, Ridge, Cantonments) | 4,500,000 – 20,000,000+ | $409,000 – $1,800,000+ | Top villas reach GHS 18–20 million |
Key observation: Building your own house (construction cost GHS 974,000 – 2,124,000) can be significantly cheaper than buying a finished house in prime Accra locations (GHS 4,500,000+). However, building requires project management expertise, time, and the ability to navigate the “completeness gap.”
The national median house price sits at GHS 1,400,000 (around USD 127,000), while the average is GHS 6,250,000 because luxury Accra listings pull it up. For 80 per cent of homes on the market, prices fall between GHS 600,000 and GHS 5,500,000 .
Part 8: International Comparisons
The cost of building a 4-bedroom house varies dramatically across countries:
| Country/Region | Estimated Build Cost (USD) | Notes |
|---|---|---|
| Ghana (Accra, turnkey finish) | $88,000 – $193,000 | Our estimate range |
| Ghana (Accra, basic 4-bedroom) | $55,000 – $109,000 (construction only) | |
| United Kingdom | $200,000 – $350,000 | Internal ASJ data |
| United States | $200,000 – $400,000 | Internal ASJ data |
| Kenya | $40,000 – $100,000 | Internal ASJ data |
| Nigeria | $35,000 – $90,000 | Internal ASJ data |
Prime Accra costs 40–60 per cent more for a comparable home. A 4-bedroom in prime Accra runs USD 450,000–600,000 versus USD 180,000–250,000 in prime Kumasi .
Part 9: Practical Recommendations for Budgeting
1. Use an Itemised Bill of Quantities (BoQ)
Do not accept a flat per-square-metre quote. Require an itemised BoQ that includes:
-
Foundation materials and labour
-
Blockwork (quantities and rates)
-
Structural steel (tonnage and grade)
-
Plastering (wall area and thickness)
-
Floor screeding (area and depth)
-
Full electrical and plumbing schedules
The GhanaHousePlanner model demonstrates that itemised estimates are 29–98 per cent higher than informal quotes—because they include everything required for a complete, code-compliant building .
2. Phase Your Construction Carefully
The Government Statistician advises: “Households planning construction should take advantage of lower prices for materials such as cement and steel, while carefully budgeting for high-cost items including glazing, plumbing and roofing sheets” .
Phasing strategy:
-
Phase 1: Foundation and structural frame (take advantage of stable cement/steel prices)
-
Phase 2: Roofing (budget extra for +13% inflation)
-
Phase 3: Electrical and plumbing (budget extra for high inflation)
-
Phase 4: Finishing (glazing, doors, painting)
3. Lock in Supplier Prices
For serious self-builders, the Government Statistician recommends “locking up supplier prices through medium-term contracts to reduce exposure to volatile material costs” .
4. Budget for High-Inflation Items
The Ghana Statistical Service specifically advises “budgeting adequately for high-inflation items including glazing, plumbing materials and roofing sheets” .
5. Include a Realistic Contingency
Industry practice recommends 15–20 per cent contingency for unanticipated cost overruns. The academic study confirms that the “completeness gap” means many builders underestimate by 30–100 per cent .
6. Use Digital Estimation Tools
The GhanaHousePlanner platform provides region-aware material pricing updated monthly, with detailed cost breakdowns across categories including steel, electrical, plumbing, and finishes. The tool is based on the validated academic model and is free for basic use .
7. Get Multiple Contractor Quotes
Request itemised quotes from at least three contractors. Compare line items. If a quote seems significantly lower than others, ask what is omitted.
ASJ Conclusion
Building a 4-bedroom house in Greater Accra in 2026 requires a realistic construction budget of between GHS 974,000 and GHS 2,124,000 (including contingency) , excluding land. This range accounts for the “completeness gap” identified in recent academic research—the systematic omission of essential components like structural steel, plastering, floor screed, and full services in informal contractor quotes .
The current economic environment offers some advantages. Cement and steel prices have declined year-on-year, with 32.5R cement at GHS 80–85 per bag and steel at GHS 19,000–25,500 per ton. Building inflation has stabilised at 2.2 per cent .
However, significant cost pressures remain. Electrical works account for over half of sector inflation. Glazing (windows) is up 16.2 per cent, plumbing up 14.5 per cent, and roofing sheets up 13 per cent. The Government Statistician’s advice is clear: phase construction carefully, lock in supplier prices where possible, and budget adequately for high-inflation items .
If you are considering buying instead of building: A finished 4-bedroom house in an emerging suburb costs at least GHS 1,200,000, rising to GHS 4,500,000+ in prime Accra locations . Building can be cheaper, but it requires project management expertise, time, and the ability to navigate the “completeness gap.”
The most important takeaway is this: If a contractor quotes you a flat per-square-metre rate that seems too good to be true, it almost certainly is. The “completeness gap” is not a conspiracy—it is a systematic failure of informal estimating. Use an itemised Bill of Quantities. Verify each line item. And build with confidence that your budget matches the real cost of a complete, code-compliant home.
Quick Reference: 2026 Construction Cost Summary
| Item | Estimated Cost (GHS) |
|---|---|
| 32.5R Cement (per bag) | 80 – 85 |
| 42.5R Cement (per bag) | ~107 |
| High tensile steel (per ton) | 19,000 – 25,500 |
| 4-bedroom house construction (excluding land) | 650,000 – 1,400,000 |
Material requirements for a 4-bedroom house:
-
Total cement bags: 1,200 – 2,000 bags
-
Estimated cement cost: GHS 96,000 – GHS 214,000
-
Total steel tonnage: 7.5 – 12 tons
-
Estimated steel cost: GHS 142,500 – GHS 306,000
| Phase | Cost Range (GHS) |
|---|---|
| Foundation & structural | 250,000 – 535,000 |
| Roofing | 157,000 – 315,000 |
| Finishing (floors, walls, paint) | 120,000 – 262,000 |
| Electrical & plumbing | 130,000 – 283,000 |
| Doors, windows, glazing | 58,000 – 140,000 |
| Contingency (15–20%) | 127,000 – 354,000 |
History and Facts Section
Ghana Construction Cost Trends (2024–2026)
| Year | Key Event | Impact |
|---|---|---|
| 2024 (H1) | Cedi depreciation, high inflation | Cement surged from GHS 85 to GHS 110 |
| 2024 (H2) | Currency stabilisation | Cement prices begin moderating |
| January 2025 | Building inflation peak | 23.7% year-on-year |
| March 2025 | Building inflation record high | 24.4% |
| December 2025 | Consecutive monthly declines | Inflation drops to 4.4% |
| January 2026 | Ninth consecutive decline | Inflation at 3.9% |
| February 2026 | GhanaHousePlanner study published | Identifies 29–98% “completeness gap” in quotes |
| April 2026 | Building inflation stable | 2.2% year-on-year |
Cement Price Timeline
| Period | 32.5R Price (per bag) | Notes |
|---|---|---|
| 2024 (H1) | GHS 85 – 110 | Peak volatility |
| Early 2026 | GHS 90 – 95 | Elevated but stable |
| June 2026 | GHS 80 – 85 | Recent decline |
Market Price Ranges for 4-Bedroom Houses (2026)
| Location Category | Price Range (GHS) | Source |
|---|---|---|
| Emerging suburbs | 1,200,000 – 2,500,000 | |
| Established suburbs | 2,500,000 – 4,500,000 | |
| Prime Accra | 4,500,000 – 20,000,000+ |
FAQ Section
Q1: How much does it cost to build a 4-bedroom house in Ghana in 2026?
A: Construction alone costs between GHS 650,000 and GHS 1,400,000 for a standard 4-bedroom house in Greater Accra, excluding land. With contingency (15–20%), the total ranges from GHS 974,000 to GHS 2,124,000.
Q2: What is the current price of cement in Ghana in 2026?
A: As of June 2026, 32.5R cement retails for GHS 80–85 per bag, while 42.5R (high-strength) cement costs approximately GHS 107 per bag .
Q3: How much steel is needed for a 4-bedroom house?
A: A typical 4-bedroom house requires 7.5–12 tons of high tensile steel reinforcement, costing between GHS 142,500 and GHS 306,000 at current prices of GHS 19,000–25,500 per ton .
Q4: What is the “completeness gap” in construction quotes?
A: The “completeness gap” is the systematic discrepancy between informal contractor quotes and actual, code-compliant construction costs. Informal quotes often omit structural steel, plastering, floor screed, and full electrical/plumbing services, resulting in underestimates of 29–98 per cent .
Q5: Is it cheaper to build or buy a 4-bedroom house in Ghana?
A: Building can be cheaper (GHS 974,000–2,124,000 for construction) compared to buying in prime Accra locations (GHS 4,500,000+). However, building requires project management expertise and time. Buying has a higher initial cost but lower risk of budget overruns .
Q6: How much does a 4-bedroom house cost in Accra in 2026?
A: A 4-bedroom house in an emerging suburb costs at least GHS 1,200,000. Established suburban areas require GHS 2,500,000 to GHS 4,500,000. Prime Accra starts significantly higher .
Q7: Are cement prices going down in Ghana?
A: Yes. Cement inflation was negative 11.2 per cent in April 2026, meaning prices have dropped compared to the same period last year. A 50kg bag of 32.5R cement now costs GHS 80–85, down from GHS 90–95 earlier in the year .
Q8: What is the most expensive component of a 4-bedroom house build?
A: Electrical works account for 52.8 per cent of total sector inflation, making it the single largest cost driver. Glazing (+16.2%), plumbing (+14.5%), and roofing sheets (+13%) are also major cost drivers .
Q9: How can I avoid cost overruns when building a house in Ghana?
A: Use an itemised Bill of Quantities (not a flat per-square-metre quote), budget 15–20 per cent contingency, phase construction, lock in supplier prices through contracts, and budget adequately for high-inflation items (electrical, glazing, plumbing, roofing) .
Q10: What does the Ghana Statistical Service advise for homebuilders?
A: “Households planning construction should take advantage of lower prices for materials such as cement and steel, while carefully budgeting for high-cost items including glazing, plumbing and roofing sheets.” Phase projects carefully and consider locking in supplier prices through medium-term contracts
Source: Accra Street Journal
Last Updated on June 14, 2026 by Samuel Kwame Boadu
Disclaimer: Some content on Accra Street Journal may be aggregated, summarized, or edited from third-party sources for informational purposes. Images and media are used under fair use or royalty-free licenses. Accra Street Journal is a subsidiary of SamBoad Publishing Hub under SamBoad Business Group Ltd, registered in Ghana since 2014.
For concerns or inquiries, please visit our Privacy Policy or Contact Page.
Samuel Kwame Boadu is a Ghanaian media entrepreneur and storyteller with a passion for amplifying urban voices and uncovering everyday truths. He is the Editor-in-Chief and Founder of Accra Street Journal, a dynamic digital platform dedicated to capturing the pulse of Ghana’s capital—its people, culture, challenges, business, sports and innovations.